S.NO. | CLIENT | NAME OF CONTRACT | BRIEF SCOPE OF WORK | VALUE OF CONTRACT | LOCATION | REMARK |
---|---|---|---|---|---|---|
1 | Sprng Energy | 400 KV S/c Transmission Line for 900 MW Solar Project. | Turnkey EPC | Sprng Energy | Deora, Jodhpur | Ongoing |
2 | Juniper Green | 220 KV S/c TL on D/c & M/c tower for 300 MW Solar Power Plant | Turnkey EPC | Juniper | Bhadla, Phalodi | Ongoing |
3 | ACME Solar | 220 KV S/c TL on D/c & M/c tower for 300 MW Solar Power Plant | Turnkey EPC | ACME | Nokha Daiya, Bikaner | Ongoing |
4 | Jakson Green | 220 KV S/c TL on D/c & M/c tower for 300 MW Solar Power Plant | Turnkey EPC | Statkraft | Randheesar, Bikaner | Ongoing |
5 | Soltown Infra | 220 KV D/c TL on D/c & M/c tower for 675 MW Solar Power Plant | Turnkey EPC | Soltown Infra | Kawani, Bikaner | Ongoing |
6 | Fourth Partner | 220 Kv S/c TL on D/c & M/c tower for 335 MW Solar Power Plant | Turnkey EPC | Fourth Partner | Kawani, Bikaner | Completed |
7 | Sprng Energy | 220 KV S/c TL on D/c towers for 200 MW Solar Project | Turnkey EPC | Sprng Energy | Barmer, Rajasthan | Completed |
8 | Prerak Greentech | 220 Kv S/c TL on D/c & M/c tower for 400 MW Solar Power Plant | Turnkey EPC | Brookfield | Kawani, Bikaner | Completed |
9 | Ashoka Buildcon (NTPC) | 132 Kv S/c TL for 150 MW Solar Project & 132 KV GSS Chhattargarh | Turnkey EPC | NTPC-REL | Chhattargarh, Bikaner | Completed |
10 | Vikram Solar (NTPC) | 220 KV S/c TL for 300 MW Solar Project | Turnkey EPC | Vikram Solar (NTPC) | Nokhra, Bikaner | Completed |
11 | Fortum Solar | 220 KV S/c TL for 260 MW Solar Project | Turnkey EPC | Fortum Solar | Bhainsada, Jaisalmer | Completed |
12 | UPC Solar | 132kV TL for 100MW Sitara Solar Power Plant | Turnkey EPC | UPC Solar | Kanaser – Jodhpur | Completed |
13 | KEC International | 400 KV S/c TL | Service | KEC International | Khetri, Rajasthan | Completed |
14 | CORE-Jodhpur Division | Railway Electrification | Turnkey EPC | Indian Railway | Barmer, Rajasthan | Completed |
15 | CORE-Jaipur Division | Railway Electrification | Turnkey EPC | Indian Railway | Sikar & Jhunjhunu, Rajasthan | Completed |
S.NO. | CLIENT | NAME OF CONTRACT | BRIEF SCOPE OF WORK | VALUE OF CONTRACT | LOCATION | REMARK |
---|---|---|---|---|---|---|
1 | NWR, Bikaner Division | 630 Kwp Rooftop Solar Power Plant at 15 Railway Stations under Amrit Bharat Scheme | Turnkey EPC | Indian Railway | Rajasthan & Haryana | Ongoing |
2 | Municipal Council, Sikar (Raj.) | Sikar (Raj.) 115 KWp Rooftop Solar Power Plant, Municipal Council Building, Sikar (Raj.) | Turnkey EPC | Rajasthan Govt. | Sikar, Rajasthan | Completed |
3 | Tata Solar Power | 5 MWp AC installation work | Solar - AC Installation work | Tata | Neemarana - Rajasthan | Completed |
4 | Vikram Solar | 40MWp AC Project AC and DC Installation work - ILFS . | Solar - AC Installation work | NTPC | Rajasthan | Completed |
5 | Adani | Design, engineering, manufacture, assemble, erection & testing of 50MW Power plant at Pavagada including supply portion. | EPC - 50MW solar power plant | SECI | Pavagada , Karnataka | Completed |
6 | Vikram Solar | 5*2 MWp Complete Electrical Installation Work With supply of Metering Equipments - Bhadla . | SECI | Bhadla , Jodhpur - Rajasthan | Completed | |
7 | Waaree | ROHA-27.5 MWp AC Installation work - Bhadla | Solar - AC Installation work | Roha Dychem | Bhadla , Jodhpur - Rajasthan | Completed |
8 | Vikram Solar | 2*65MWp AC and DC Installation work - NTPC - Bhadla | Solar - AC/DC Installation work | NTPC | Bhadla , Jodhpur - Rajasthan | Completed |
9 | Vikram Solar | 40MWp Electrical Installation Work. | Solar - AC Installation work | NTPC | Charnka - Gujarat | Completed |
10 | Vikram Solar | 10 MWp DC installation work | Solar - DC Installation work | NTPC | Rajasthan | Completed |
11 | Waaree | 2*10MWp Electrical Installation Work With Supply - Jindal | Solar - DC Installation work | HFE | Rajasthan | Completed |
12 | L&T , Construction | Sunedison - 37.5MWp SPV Project/AC installation work | Solar - AC Installation work | Sunedison | Rajasthan | Completed |
13 | Rays Experts | 30MWp Electrical DC & AC Work including Misscalenous items supply at Gajner & Kolayat,Bikaner | Solar - AC/DC Installation work | Rays Expert | Kolayat & Gajner - Rajasthan | Completed |
S.NO. | CLIENT | NAME OF CONTRACT | BRIEF SCOPE OF WORK | VALUE OF CONTRACT | LOCATION | REMARK |
---|---|---|---|---|---|---|
1 | Vikram Solar | Substation Building Work – Bhadla -2*5 MWp SPV | Civil Scope | NTPC | Bhadla , Jodhpur - Rajasthan | Completed |
2 | Adani | Kamuthi Piling and RCC Work | Supply & installation of civil Scope | SECI | Kamuthi , Tamilnadu | Completed |
3 | Vikram Solar | NTPC Bhadla Piling and Building Work | Supply & installation of civil Scope | NTPC | Bhadla , Jodhpur - Rajasthan | Completed |
4 | Jakson | NTPC_Bhadla_Building,Piling and foundation work | Supply & installation of civil Scope | NTPC | Bhadla , Jodhpur - Rajasthan | Completed |
5 | Vikram Solar | NGSPICL Charnka - Gujrat Piling and Building Work | Supply & installation of civil Scope | GSPICL | Charnka - Gujarat | Completed |
6 | Adani | 40 MWp Completed civil work | Supply & installation of civil Scope | RVPNL | Rajasthan | Completed |
7 | Adani | Chhattisgarh - Piling Work for Solar Structure | Supply & installation of civil Scope | SECI | Chhattisgarh | Completed |
8 | Adani | Civil Scope - Kanasar | Supply & installation of civil Scope | SECI | Kanasar - Rajasthan | Completed |
9 | GE | Civil Piling Work – Hanur Solar Park | Supply & installation of civil Scope | ECOREN | Hanur- Karnataka | Completed |
10 | ACME | Civil Piling & Civil Work – Bhadla Solar Park | Supply & installation of civil Scope | SECI | Bhadla , Jodhpur - Rajasthan | Completed |
11 | L&T | Civil Piling & Civil Work – Bhadla Solar Park | Supply & installation of civil Scope | SECI | Bhadla , Jodhpur - Rajasthan | Completed |
12 | Avaada | 25MW - Civil Piling & Civil Work – Bhadla Solar Park | Supply & installation of civil Scope | SECI | Bhadla , Jodhpur - Rajasthan | Completed |
S.NO. | CLIENT | NAME OF CONTRACT | BRIEF SCOPE OF WORK | VALUE OF CONTRACT | LOCATION | REMARK |
---|---|---|---|---|---|---|
1 | GE T&D | 400kV Grid station – RSS – Civil Scope | ETC– Civil | Azure Power | Jamsar , Bikaner - Rajasthan | Completed |
2 | GE T&D | 400kV Grid station – RSS – Electrical Erection | ETC– Electrical | Azure Power | Jamsar , Bikaner - Rajasthan | Completed |
3 | Adani Rawara | 220kV Pooling substation | ETC | MSEDCL | Rawara - Rajasthan | Completed |
4 | Adani Hybrid | 220kV Pooling substation | ETC | MSEDCL | Rawara - Rajasthan | Completed |
5 | Adani NTPC | 220kV Pooling substation | ETC | MSEDCL | Rawara - Rajasthan | Completed |
6 | Eden Renewables | 220 KV GSS, Lakhasar | ETC | Eden Renewables | Lakhasar, Jaisalmer | Completed |
7 | Ashoka Buildcon (NTPC) | 132kV Switchyard installation | ETC | Ashoka Buildcon (NTPC) | Chhattargarh, Rajasthan | Completed |
8 | Jakson | 132kV Switchyard installation | ETC | NTPC | Rajasthan | Completed |
9 | GE - Global | 132kV Switchyard installation | ETC | Tata - Fortum | Rajasthan | Completed |
10 | Vikram Solar | 132kV Switchyard installation | ETC | Vikram Solar | Bhadla , Jodhpur | Completed |
11 | Vikram Solar | 220kV Switchyard installation | ETC | Vikram Solar | Nokhara, Bikaner | Completed |
12 | Azure Power | 400 KV Substation | ETC | Azure Power | Bikaner , Rajasthan | Completed |
13 | Bhadja Transmission Private Limited | 33kV Bay installation including material supply with Electrical inspector approval | Substation erection , commissioning , testing & approval | In House | Rajasthan | Completed |
14 | Rays Experts | Construction of 33KV - 5KM TL on ISMB . | 33kV Transmission line construction | In House | Rajasthan | Completed |
15 | ILFS | 132 KV & 11KV T.L Route Survey and Planning and 11 KV Line Shifting. | OHL Survey | ILFS | Rajasthan | Completed |
16 | Adani | TL Route Survey and Planning. | OHL Survey | SECI | Rajasthan | Completed |
17 | Saurya Urja – ILFS | 80kW Solar Rooftop EPC at Bhadla | Solar Rooftop | Suarya Urja | Bhadla , Jodhpur | Completed |
18 | Mahindra | 12.5 MW AC / DC with CEIG liasoning work | AC / DC with liasoning | SECI | Bhadla , Jodhpur | Completed |
19 | Avaada | 25 MW AC / DC with CEIG liasoning work | AC / DC with liasoning | SECI | Bhadla , Jodhpur | Completed |
20 | Patton, India | 132kV Line survey , Sikar Rajasthan | OHL Survey | RVPNL | Sikar , Rajasthan | Completed |
21 | Fortum India | 220kV DC Transmission Line | Turnkey EPC | SECI | Pokhran - Rajasthan | Completed |
22 | RRB Energy | Wind Jaisalmer - Supply of ABT meter | Supply of RBT meter | Jaisalmer , Rajasthan | Completed | |
23 | Vikram Solar Ltd. | 2.6 MWp – Bhageria industries –Ahmednagar. | Turnkey EPC | Bhageria Industries | Ahmednagar | Completed |
24 | Adani | 150 MW – AC Supply & Installation work | I & C | GUVNL | Kutch – Gujarat | Completed |
25 | UPC Solar | 132kV TL for 100MW Sitara Solar Power Plant | Turnkey EPC/td> | UPC Solar | Kanaser – Jodhpur | Completed |
26 | Saurya Urja Rajasthan Ltd. | Work for Shifting 33kV OHL Line falling inside solar Park | OHL Shifting Work | Suarya Urja | Bhadla , Jodhpur | Completed |